System Integration ProjectApplication of PERT/CPMTwo international banks are integrating two financial processing software systems as a result of their merger. Preliminary analysis and interviews with all parties involved resulted in the following project information. The “systems integration team” for this project plans to define and manage this project on two levels. The following activities represent an aggregate view, and within each activity is a more detailed view with subtasks and project networks defined. All times are in weeks.Activity Immediate TimePredecessorsA — 3B A 1C A 2D B, C 3E C 5F C 3G E 7H E, F 5I D, G, H 8As a member of the systems integration team, you have operations managementresponsibilities. You have been tasked to develop a detailed project plan, toidentify alternative project completion dates, and to recommend an optimal projectdeadline to top management.You should start with a Gantt Chart that will keep top management temporarilycontent, while you prepare your PERT/CPM analysis. You need an Activities TimeRequirements Table, a Critical Task and Slack Time Table, and a PERT/CPMNetwork Diagram that displays the critical path. Of course, you will prepare areport for top management with the Background of this systems project, the projectdeadline Issue to be resolved, the three project deadline Alternatives, anAnalysis of the three Alternatives, and your Recommendation.Attached to your report should be a Gantt Chart, Activities TimeRequirements Table, a Critical Task and Slack Time Table, and a PERT/CPMNetwork Diagram – 4 Attachments.